We are in the process of preparing the final phases to complete the migration to our new data centre in Bologna, Italy.
Whilst the migration has progressed with a minimum level of disruption to date, we are now approaching a phase when some degradation of the services is to be expected.
Here we will keep ECMWF users informed about the data centre move to Bologna, update on
Warning |
---|
This is work in progress. More information will be added as soon as it becomes available. |
Table of Contents |
---|
Warning |
---|
To get notified of any changes to this page, please log in and click on in the upper right. |
The purpose of this space is to keep users of ECMWF services informed about the move to the new data centre, update them any service disruptions or degradation this might cause and to highlight any action user you might need to take.
General
HPCF (and ecgate)
The Atos system...
Who is affected?
Action to take
We will also engage with you to participate in the testing and migration when services you use start running in parallel in Bologna, for you to test and facilitate the migration.
Please check the information provided below for any service you might use.
DHS Move
DHS move(MARS and ECFS)
The Data Handling System
(DHS),
providingwhich provides the MARS and ECFS services,
needs to be moved to Bologna before the new Atos HPCF will produce an increased archive load. A detailed migration timeline is shown in the transition plan where all events are relative to day D, the day when the access to MARS and ECFS in Reading will be switched off. The DHS move is expected to last up to 4 weeks. To minimise the impact of the move, essential data, necessary to continue operational and time-critical activities, has been identified and archived in a Temporary-DHS. In preparation of the DHS move we will conduct a number of dry-runs, during which the access to the main DHS in Reading will be blocked. The purpose of the dry runs is to verify that the Temporary-DHS contains all essential data necessary to continue all critical activities during the move. Some of the dry-runs will last for 1-2 days. A final longer dry-run, lasting 5-7 days, is expected to happen 4 weeks before the move and will help to establish the exact date of day D.Main service disruptions
The table below gives an indication on the service disruptions foreseen as part of the DHS-Move.
with data becoming gradually available again during the move
Impact to MARS service
No impact expected
The following services/data are not expected to be impacted by the dry-runs and the DHS-Move:
- Operational Forecast Production (Everything listed in the Catalogue of ECMWF real-time products, ERA5T, CAMS, …)
- Access to recent operational data (verification time less than 1 month in the past)
- Archiving into MARS
- MS Time-critical suites
- Atos HPC Alpha/Beta testing
Any other access to services/data will be affected as described below.
Degradation of service/data access
The following services/access to data will be degraded during dry-runs and the DHS-move
- WebAPI registered (private)
- MARS
- ERA5 BX production
Unavailability of service/data
The following services/data are not expected to be available during dry-runs and the DHS-move:
- WebAPI public
- ADS/CDS external
- Public datasets TIGGE/S2S/
- IFS Research experiments
- Historical data: Operational data, ERA5
Impact to ECFS service
During dry-runs and the DHS move access to data archived in ECFS which has not been identified as essential is not expected to be available. However, archiving into ECFS should not be affected by the DHS migration.
Recommended user action
- Users of MARS and ECFS are urged to check if and how their work might be affected by the DHS-Move and plan accordingly.
- Major changes to production processes etc. are best avoided during this period. For some activities the best course of action might be to avoid the migration period entirely...
Recent space activity
Recently Updated | ||||||||
---|---|---|---|---|---|---|---|---|
|
is one of the few data centre components which will physically move from Reading to Bologna. In particular the move of tapes will inevitably cause some degradation to these services. See how the DHS-Move might affect your data access >>
Migration of data dissemination (ECPDS)
As part of our Data Centre move we have started the installation of ECPDS, the ECMWF Production Data Store, in Bologna, Italy. The migration of this system will affect all sites receiving ECMWF data via the dissemination and requires some changes on the user's side. See Migration of data dissemination (ECPDS) >>
Migration to Atos HPC
The new Atos will not only replace the current HPC service provided by the Cray XC40 systems, but also all Linux servers, e.g. ecgate. Migration to Atos HPC >>
Migration of the operational forecast to Atos
In preparation of the switch of the operational forecast production from the Cray to the Atos HPC, pre-operational test data will be provided well ahead of the switch, see Implementation of IFS Cycle 47r3 on Atos >>